Created page with "__notoc__ {{OR/14/014}} ==Aircraft and equipment== ===Aircraft and Geophysical on-board equipment=== Aircraft : Reims F406 Operator..."
 
Dbk (talk | contribs)
No edit summary
Line 3: Line 3:
==Aircraft and equipment==
==Aircraft and equipment==
===Aircraft and Geophysical on-board equipment===
===Aircraft and Geophysical on-board equipment===
{|
| Aircraft||:||Reims F406
|-
| Operator||:||CGG AIRBORNE SURVEY
|-
| Registration||:||ZS-SSC
|-
| Survey Speed||:||140 knots
|-
| Magnetometer (x3)||:||Scintrex CS-3 single cell caesium vapour, wing pod(s) and/or tail stinger installation, sensitivity = 0.01 nT , sampling rate = 0.5 s, ambient range 20,000 to 100,000 nT. The general noise envelope was kept below 0.5 nT.
|-
| Digital Acquisition||:||FASDAS
|-
| Radar Altimeter||:||Honeywell KRA405B
|-
| Camera||:||Digital camera.
|-
| Electronic Navigation||:||Novatel OEMV-3 & Omnistar DGPS
|}


===Base Station Equipment===
{|
| Magnetometer||:||Scintrex CS-3 single cell caesium vapour, mounted in a magnetically quiet area, measuring the total intensity of the earth’s magnetic field in units of 0.01 nT at intervals of 0.5 sec, within a noise envelope of 0.20 nT.
|-
| GPS Receiver||:||NovAtel OEM4, measuring all GPS channels, for up to 12 satellites.
|-
| Computer||:||Laptop, Pentium model.
|-
| Data Logger ||:||CF1, SBBS (single board base station).


===Data Processing equipment===
{|
| Computer||:||Laptop computer.
|-
| Printer||:||Portable inkjet printer.
|-
| DVD writer Drive||:||Internal DVD+RW format.
|-
| Hard Drive||:||1024 GB Removable hard drive.
|}


Aircraft                                  :    Reims F406
==Survey aquisition progress==
 
{| class="wiktiable"
 
|+  Table 4 Project Acquisition Progress
 
| colspan="2" | <p align="center">'''PROJECT ACQUISITION FIGURES'''</p>
Operator                                :    CGG AIRBORNE SURVEY
 
 
 
Registration                            :    ZS-SSC
 
 
 
Survey Speed                        :    140 knots
 
 
 
 
 
 
 
Magnetometer (x3)                : Scintrex CS-3 single cell caesium vapour, wing pod(s) and/or tail stinger installation, sensitivity = 0.01 nT , sampling rate = 0.5 s, ambient range 20,000 to 100,000 nT. The general noise envelope was kept below 0.5 nT.
 
 
 
Digital Acquisition                :    FASDAS
 
 
 
Radar Altimeter                      :    Honeywell KRA405B
 
 
 
Camera                                  :    Digital camera.
 
 
 
Electronic Navigation            :    Novatel OEMV-3 & Omnistar DGPS
 
 
 
 
 
 
 
name="_TOC_250062"
 
 
 
''' '''
 
 
 
Magnetometer                            :  Scintrex CS-3 single cell caesium vapour, mounted in a magnetically quiet area, measuring the total intensity of the earth’s magnetic field in units of 0.01 nT at intervals of 0.5 sec, within a noise envelope of 0.20 nT.
 
 
 
GPS Receiver                        :    NovAtel OEM4, measuring all GPS channels, for up to 12 satellites. Computer                                :    Laptop, Pentium model.
 
 
 
Data Logger                            :    CF1, SBBS (single board base station).
 
 
 
 
 
 
 
 
 
 
 
name="_TOC_250061"
 
 
 
''' '''
 
 
 
Computer                                :    Laptop computer.
 
 
 
Printer                                      :    Portable inkjet printer. DVD writer Drive                            :    Internal DVD+RW format.
 
 
 
Hard Drive                            :    1024 GB Removable hard drive.
 
 
 
 
 
 
 
 
 
 
 
name="_TOC_250060"
 
 
 
''' '''
 
 
 
''' '''
 
{| cellspacing="0" cellpadding="0" border="0"
| colspan="2" | <p align="center">'''PROJECT'''''' ''''''ACQUISITION'''''' ''''''FIGURES'''</p>
|-
|-
| Total survey line kilometres Accepted
| Total survey line kilometres Accepted
Line 126: Line 56:
|}
|}


Table 4 Project Acquisition Progress
{| class="wikitable"
 
|+ Table 5 Project Downtime Figures
{| cellspacing="0" cellpadding="0" border="0"
| colspan="2" | <p align="center">'''PROJECT DOWNTIME FIGURES'''</p>
| colspan="2" | <p align="center">'''PROJECT'''''' ''''''DOWNTIME'''''' ''''''FIGURES'''</p>
|-
|-
| Total days flown
| Total days flown
Line 136: Line 65:
| Lost days due to Weather Influence
| Lost days due to Weather Influence
| <p align="center">77.25</p>
| <p align="center">77.25</p>
|}
|-
</div> <br clear="all">  <div>
{| cellspacing="0" cellpadding="0" border="0"
| Lost days due to Excessive Diurnal activity
| Lost days due to Excessive Diurnal activity
| <p align="center">0</p>
| <p align="center">0</p>
Line 157: Line 84:
| <p align="center">0</p>
| <p align="center">0</p>
|-
|-
| Lost days due to Logistics
| Lost days due to Logistics <br>(Permits, security, fuel shortages, unrest)
 
 
 
(Permits, security, fuel shortages, unrest)
| 4.25 ''(2 Days Total Invoice able)''
| 4.25 ''(2 Days Total Invoice able)''
|-
|-
Line 167: Line 90:
| <p align="center">0</p>
| <p align="center">0</p>
|}
|}
{{clear}}
[[Image:14014fig11a.jpg|thumb|500px|'''Figure 11''' Production.]]
{{clear}}


Table 5 Project Downtime Figures
==Airborne system==
 
[[Image:14014 fig12.jpg|thumb|500px|'''Figure 12''' Airborne system.]]
 
 
 
 
 
 
[[File:C:\Users\dbk\AppData\Local\Temp\msohtmlclip1\01\clip_image002.jpg|590px]]
 
 
 
 
 
 
 
Figure 11: Production
</div> <br clear="all">  <div>
name="_TOC_250059"
 
 
 
''' '''
 
 
 
''' '''
 
 
 
[[File:C:\Users\dbk\AppData\Local\Temp\msohtmlclip1\01\clip_image004.jpg|488px]]
 
 
 
Figure 12: Airborne system
 
 
 
 
 
 
 
name="_TOC_250058"
 
 


==Tests and calibration==
Important checks were performed before, during and after the data acquisition stage to ensure that the data quality was in keeping with the survey specifications. The following outlines the Quality Control measures conducted throughout the acquisition phase of the survey.
Important checks were performed before, during and after the data acquisition stage to ensure that the data quality was in keeping with the survey specifications. The following outlines the Quality Control measures conducted throughout the acquisition phase of the survey.


 
===System log===
 
 
 
 
 
name="_TOC_250057"
 
 
 
The difference between the time a reading is taken and the time it is stored, due to computer processing time and position of the different sensors relative to the GPS antenna was determined in the field. See Appendix 3 for the lag value of the different geophysical systems.
The difference between the time a reading is taken and the time it is stored, due to computer processing time and position of the different sensors relative to the GPS antenna was determined in the field. See Appendix 3 for the lag value of the different geophysical systems.


 
===Magnetic tests and calibration
 
====MAGNETOMETER COMPENSATION (FOM)====
 
 
 
 
name="_TOC_250056"
 
 
 
''' '''
 
 
 
1.4.2.1      MAGNETOMETER COMPENSATION (FOM)
 
 
 
The compensation procedure involved the flying, at altitude, over a magnetically quiet area, undertaking aircraft manoeuvres, rolls ± 10°, pitches ± 5° and yaws ± 5°, along headings parallel to the traverse and control line trends. A fluxgate magnetometer monitored these manoeuvre noise effects and the compensator accumulated the results. The compensator returned a Figure of Merit (FOM) value, results of which are presented in Appendix 3.
The compensation procedure involved the flying, at altitude, over a magnetically quiet area, undertaking aircraft manoeuvres, rolls ± 10°, pitches ± 5° and yaws ± 5°, along headings parallel to the traverse and control line trends. A fluxgate magnetometer monitored these manoeuvre noise effects and the compensator accumulated the results. The compensator returned a Figure of Merit (FOM) value, results of which are presented in Appendix 3.


 
====PARALLAX CONTROL====
 
 
 
 
 
1.4.2.2      PARALLAX CONTROL
 
 
 
Before the commencement of the survey several lines were flown at standard speed and flying height in opposite directions over a suitable, well controlled magnetic anomaly to establish the parallax of the system (spatial relationship between GPS and magnetometer readings).
Before the commencement of the survey several lines were flown at standard speed and flying height in opposite directions over a suitable, well controlled magnetic anomaly to establish the parallax of the system (spatial relationship between GPS and magnetometer readings).


The system noise was measured and recorded at the project site before the survey started, see Appendix 3.
The system noise was measured and recorded at the project site before the survey started, see Appendix 3.


 
====HEADING TEST====
 
 
 
 
 
1.4.2.3      HEADING TEST
 
 
 
The results of the heading test are presented in Appendix 3.
The results of the heading test are presented in Appendix 3.


 
===Altimeter calibration===
 
 
 
 
 
name="_TOC_250055"
 
 
 
The radar altimeter was calibrated at the start of the survey. See tabulated results in Appendix 3.
The radar altimeter was calibrated at the start of the survey. See tabulated results in Appendix 3.
</div> <br clear="all">
</div> <br clear="all">


name="_TOC_250054"
==Quality control of production data==
 
===Intital field===
 
 
''' '''
 
 
 
name="_TOC_250053"
 
 
 
At the completion of each day’s flying an initial review of the data was performed in the field. This process was primarily to ensure all the equipment was functioning properly and enables the crew to immediately ascertain that production can resume the following day. This process does not necessarily determine if the data were within specifications. Priority was given to getting the data back to the office where a more thorough analysis of the data was performed. A list of the steps of the initial field review of the data follows:
At the completion of each day’s flying an initial review of the data was performed in the field. This process was primarily to ensure all the equipment was functioning properly and enables the crew to immediately ascertain that production can resume the following day. This process does not necessarily determine if the data were within specifications. Priority was given to getting the data back to the office where a more thorough analysis of the data was performed. A list of the steps of the initial field review of the data follows:
# All digital files were confirmed to be readable and free of defects.
# The integrity of the airborne data was checked through statistical analysis and graphically viewed in profile form. Any null values or unreasonable noise levels were identified.
# All altimeter and positional data were checked for any inconsistency, invalid values and spikes.
# The base station files were examined for validity and continuity. The data extent was confirmed to cover the entire acquisition period.
# The diurnal data were examined for any noise events or spiking.
# Flight path video files were visually checked for quality and to confirm the full coverage for the survey flight.
# Duplicate backups of all digital files were created.


 
===Data checking and editing===
 
1)              All digital files were confirmed to be readable and free of defects.
 
 
 
2)              The integrity of the airborne data was checked through statistical analysis and graphically viewed in profile form. Any null values or unreasonable noise levels were identified.
 
 
 
3)              All altimeter and positional data were checked for any inconsistency, invalid values and spikes.
 
 
 
4)              The base station files were examined for validity and continuity. The data extent was confirmed to cover the entire acquisition period.
 
 
 
5)              The diurnal data were examined for any noise events or spiking.
 
 
 
6)              Flight path video files were visually checked for quality and to confirm the full coverage for the survey flight.
 
 
 
7)              Duplicate backups of all digital files were created.
 
 
 
 
 
 
 
name="_TOC_250052"
 
 
 
All acquired data were thoroughly checked at each field base prior to delivery to the Johannesburg processing centre, including checking of line and flight numbers and spike checking in all major data channels. Upon receipt of the data in Johannesburg, these procedures were repeated, beginning again from the raw (untouched) data and providing a backup check of data quality.
All acquired data were thoroughly checked at each field base prior to delivery to the Johannesburg processing centre, including checking of line and flight numbers and spike checking in all major data channels. Upon receipt of the data in Johannesburg, these procedures were repeated, beginning again from the raw (untouched) data and providing a backup check of data quality.


 
The line data was checked for noise, flight path separation, height deviation, gaps and spikes using in-house CGG ATLAS software. The magnetic diurnal was checked and later corrected as described in [Part 3: Data Processing | OR/14/014 Part 3: Data Processing].
 
The line data was checked for noise, flight path separation, height deviation, gaps and spikes using in-house CGG ATLAS software. The magnetic diurnal was checked and later corrected as described in section 4.1.2 below.
 
 


All lines passed the basic QC check.
All lines passed the basic QC check.


 
===Line spacing control===
 
 
 
 
 
name="_TOC_250051"
 
 
 
Standard quality control routines were applied to highlight deviations from the planned flight path that exceed survey specification. These are accepted if a valid safety or other acceptable reason for the deviation is given in the flight log.
Standard quality control routines were applied to highlight deviations from the planned flight path that exceed survey specification. These are accepted if a valid safety or other acceptable reason for the deviation is given in the flight log.


 
===Height control===
 
The survey was acquired on a drape surface. The figure 'Map of the height deviation from planned drape' in Appendix 3 presents the deviation from the planned drape.
 
 
 
 
name="_TOC_250050"
 
 
 
The survey was acquired on a drape surface. The figure “Map of the height deviation from planned drape” in Appendix 3 presents the deviation from the planned drape.


        
        
[[Category:OR/14/014 TellusSW: airborne geophysical data and processing report | 03]]
[[Category:OR/14/014 TellusSW: airborne geophysical data and processing report | 03]]

Revision as of 12:16, 8 April 2015

Beamish D and White J. 2014. TellusSW: airborne geophysical data and processing report . British Geological Survey Internal Report, OR/14/014.

Aircraft and equipment

Aircraft and Geophysical on-board equipment

Aircraft : Reims F406
Operator : CGG AIRBORNE SURVEY
Registration : ZS-SSC
Survey Speed : 140 knots
Magnetometer (x3) : Scintrex CS-3 single cell caesium vapour, wing pod(s) and/or tail stinger installation, sensitivity = 0.01 nT , sampling rate = 0.5 s, ambient range 20,000 to 100,000 nT. The general noise envelope was kept below 0.5 nT.
Digital Acquisition : FASDAS
Radar Altimeter : Honeywell KRA405B
Camera : Digital camera.
Electronic Navigation : Novatel OEMV-3 & Omnistar DGPS

Base Station Equipment

Magnetometer : Scintrex CS-3 single cell caesium vapour, mounted in a magnetically quiet area, measuring the total intensity of the earth’s magnetic field in units of 0.01 nT at intervals of 0.5 sec, within a noise envelope of 0.20 nT.
GPS Receiver : NovAtel OEM4, measuring all GPS channels, for up to 12 satellites.
Computer : Laptop, Pentium model.
Data Logger : CF1, SBBS (single board base station).

Data Processing equipment

Computer : Laptop computer.
Printer : Portable inkjet printer.
DVD writer Drive : Internal DVD+RW format.
Hard Drive : 1024 GB Removable hard drive.

Survey aquisition progress

Table 4 Project Acquisition Progress

PROJECT ACQUISITION FIGURES

Total survey line kilometres Accepted

60 323

Total Flying Hours

415.2

Table 5 Project Downtime Figures

PROJECT DOWNTIME FIGURES

Total days flown

44

Lost days due to Weather Influence

77.25

Lost days due to Excessive Diurnal activity

0

Lost days due to Aircraft Mechanical Issues

15.25

Lost days due to Electronical Issues

1

Lost days due to Data / System Noise

0.5

Lost days due to sickness, injuries or other HSEQ Incidents

0

Lost days due to mandatory Pilot Down Days

0

Lost days due to Logistics
(Permits, security, fuel shortages, unrest)
4.25 (2 Days Total Invoice able)
Lost days due to 3rd Party Influence

0

Figure 11 Production.

Airborne system

Figure 12 Airborne system.

Tests and calibration

Important checks were performed before, during and after the data acquisition stage to ensure that the data quality was in keeping with the survey specifications. The following outlines the Quality Control measures conducted throughout the acquisition phase of the survey.

System log

The difference between the time a reading is taken and the time it is stored, due to computer processing time and position of the different sensors relative to the GPS antenna was determined in the field. See Appendix 3 for the lag value of the different geophysical systems.

===Magnetic tests and calibration

MAGNETOMETER COMPENSATION (FOM)

The compensation procedure involved the flying, at altitude, over a magnetically quiet area, undertaking aircraft manoeuvres, rolls ± 10°, pitches ± 5° and yaws ± 5°, along headings parallel to the traverse and control line trends. A fluxgate magnetometer monitored these manoeuvre noise effects and the compensator accumulated the results. The compensator returned a Figure of Merit (FOM) value, results of which are presented in Appendix 3.

PARALLAX CONTROL

Before the commencement of the survey several lines were flown at standard speed and flying height in opposite directions over a suitable, well controlled magnetic anomaly to establish the parallax of the system (spatial relationship between GPS and magnetometer readings).

The system noise was measured and recorded at the project site before the survey started, see Appendix 3.

HEADING TEST

The results of the heading test are presented in Appendix 3.

Altimeter calibration

The radar altimeter was calibrated at the start of the survey. See tabulated results in Appendix 3.


Quality control of production data

Intital field

At the completion of each day’s flying an initial review of the data was performed in the field. This process was primarily to ensure all the equipment was functioning properly and enables the crew to immediately ascertain that production can resume the following day. This process does not necessarily determine if the data were within specifications. Priority was given to getting the data back to the office where a more thorough analysis of the data was performed. A list of the steps of the initial field review of the data follows:

  1. All digital files were confirmed to be readable and free of defects.
  2. The integrity of the airborne data was checked through statistical analysis and graphically viewed in profile form. Any null values or unreasonable noise levels were identified.
  3. All altimeter and positional data were checked for any inconsistency, invalid values and spikes.
  4. The base station files were examined for validity and continuity. The data extent was confirmed to cover the entire acquisition period.
  5. The diurnal data were examined for any noise events or spiking.
  6. Flight path video files were visually checked for quality and to confirm the full coverage for the survey flight.
  7. Duplicate backups of all digital files were created.

Data checking and editing

All acquired data were thoroughly checked at each field base prior to delivery to the Johannesburg processing centre, including checking of line and flight numbers and spike checking in all major data channels. Upon receipt of the data in Johannesburg, these procedures were repeated, beginning again from the raw (untouched) data and providing a backup check of data quality.

The line data was checked for noise, flight path separation, height deviation, gaps and spikes using in-house CGG ATLAS software. The magnetic diurnal was checked and later corrected as described in [Part 3: Data Processing | OR/14/014 Part 3: Data Processing].

All lines passed the basic QC check.

Line spacing control

Standard quality control routines were applied to highlight deviations from the planned flight path that exceed survey specification. These are accepted if a valid safety or other acceptable reason for the deviation is given in the flight log.

Height control

The survey was acquired on a drape surface. The figure 'Map of the height deviation from planned drape' in Appendix 3 presents the deviation from the planned drape.