Created page with "__NOTOC__ {{OR/14/061}} The original project plan was to complete within 2 years hitting the following milestones each 6 months. Image:OR14061fig1arrows.jpg|frameless|cent..." |
m 1 revision imported |
(No difference)
|
Revision as of 11:35, 19 February 2016
Watson, C, Baker, G, and Nayembil M. 2014. Open geoscience data models: end of project report. British Geological Survey Internal Report, OR/14/061. |
The original project plan was to complete within 2 years hitting the following milestones each 6 months.

In reality the plan had to evolve as the project got underway due to circumstances beyond the control of the project team, more fully described in the following sections. The main deviations from the initial plan were the extension of the project duration from two to three years, although no extra funding was sought. Digital outputs were produced quicker and with more metadata than initially anticipated, whilst technical visits were more difficult to arrange than expected.